Building control applications and requests
Commencement and completion of building works
When your application is submitted, you will be provided with an inspection notification framework, stating the notifications we require. This will allow us to inspect the works and minimise the risk of non-compliance with the Building Regulations.
For all types of work, you should give us written notice at least two days before you start the work.
You or your contractor must provide us with the contractors contact details. You can do so using the Contractor details form.
From 1 October 2023, you are also required to notify us at the point where work is deemed to have legally begun:
- For extensions / new buildings, this is when all substructure work and the ground floor is completed
- For other type of work, it is when 15% of the work is completed
You can notify us via the Commencement of works form.
When you consider the work complete, you should, within five days, provide us with a completion notice to allow us to inspect the work for any issues before awarding the completion certificate.
This notification should take the form of a notice signed by the client, designer and builder confirming that the work has been carried out in compliance with building regulations. See, Notice of Completion form.
Without this signed notice, we cannot issue a completion certificate for the work.